How to Review a Lot Concession for Vacuum Pump Replacement Parts
When a shipment includes an approved exception for a replacement part, match the written disposition to the identified units before releasing them. Keep the reported result, the released drawing and the one-time decision traceable as separate records.

By Geetai Precision
- Published
- Updated
Contain the affected units at receiving
Consider a delivery of authorized replacement components with a report showing an out-of-requirement result on part of the lot. Ask receiving to hold the affected and uncertain identities while quality obtains the written disposition. Capture the part number, revision, order line, affected feature, actual value or condition and how the supplier identified each unit.
JPL's supplier clause QC120 is an example of a system that separates rework to meet requirements from a use-as-is decision. It calls for segregation and assigns different approval and reporting steps to different dispositions.
NASA Marshall's quality procedure describes acceptance under concession by the relevant authority, retention of nonconformance and action records, and reinspection after correction under the applicable quality plan. Those documents describe their respective programs. The industrial purchase must identify its own governing documents and approving roles.
A checklist for the release decision
Check the approval against the parts in front of you. The useful question is which units the named approver released, for which use and under what conditions. Reconcile the signed disposition, packing evidence and serial or lot identification before sending parts to stock or an installation point.
| Receiving situation | Record to compare | Disposition step |
|---|---|---|
| Affected units still mixed | Physical identities and the supplier’s segregation or shipment map | Hold the uncertain group until the covered units can be isolated. |
| Use-as-is for specific units | Written approval, exact serials or lot subset and any installation limits | Release only the identities and use covered by the approval. |
| Rework proposed or completed | Approved instructions and inspection evidence for the corrected condition | Keep the unit on hold until the responsible reviewer accepts the new evidence. |
| Approval restricted by order, date or application | Order line, dates and stated equipment or use restriction | Send any mismatch to the approving authority for a separate decision. |
| New order with the same issue | Current drawing issue and any new approval for the new order | Apply the current released requirements and treat the new occurrence separately. |
Carry the decision into service and purchasing
Retain the original result with the approval reference and the eventual stock or installation identity. Where a permitted condition restricts use, make the restriction visible to the people issuing the part. If an affected unit has already been installed, follow the buyer's containment and escalation procedure.
For a future order, start with a non-confidential summary of the part and acceptance need. Agree confidentiality and file transfer before sharing controlled drawings or sensitive concession records. Confirm who decides exceptions and which records will be included at delivery.
Inspection scope and documentation are defined during quotation according to drawing requirements and application needs.
Frequently asked questions
Can I use the previous concession on the next order?
Compare the scope stated in the written decision. If the new order or identities fall outside it, apply the released requirements and obtain a new decision for any exception.
Should the inspection report be changed to show a pass?
Retain the actual result and link the disposition. The receiving record should show which units were accepted by the named approval and which remain on hold.
Related review paths
More from Blog
References
- QC120, Nonconformance Processing and Material Review — NASA Jet Propulsion Laboratory Supplier Portal. Accessed 2026-11-12T02:31:51.319Z.
- MPR 1280.10, Marshall Quality Management System, Section 2.8.6 — NASA Marshall Space Flight Center. Accessed 2026-11-12T02:31:51.319Z.