Technical insight

Impeller Passage Borescope Inspection Records: A Buyer Checklist

Ask for a passage map linked to reviewable images and an explicit list of areas left unseen. Before ordering, agree how each visual observation will be located, reviewed and closed. Keep the dimensional acceptance plan and any application approval as separately identified requirements.

Curved blades and open passages surrounding a raised central bore
Owner-supplied geometry reference for passage identification; no borescope inspection, factory activity or delivered case depicted

Define the visual question before the route

For a machined impeller, identify the visual conditions the order requires the inspector to assess: for example, apparent loose debris, an edge condition or a surface indication needing review. Have the drawing authority supply the criteria and disposition owner. Avoid a blanket request for a video showing that the part is good.

Waygate describes selecting insertion-tube dimensions, optical viewing angle and focus range for the application. It also describes tagging recorded images and videos with where and when they were captured. [1]

Use that context to request a marked passage map, an agreed viewing route and linked files. The worksheet below is original purchasing guidance; the responsible inspector and technical reviewer must approve the actual method and criteria.

A passage-by-passage evidence worksheet

Record itemEvidence to agreeResponse to a gap
Part and passage identityPart identifier, drawing revision, passage labels, viewing side and a fixed orientation reference.Resolve an ambiguous passage label before using its images for disposition.
Required visual coverageMark the required blade faces, passage ends and root or hub transitions; link each region to files or video time references.List unseen or obscured regions individually and request an approved access alternative or scope disposition.
Observed indicationRetain a locating overview and a closer view of the same identified area, with an observation description and original file reference.Keep an unclassified indication open for the named technical reviewer; do not diagnose it from a thumbnail.
Viewing conditionsRecord the scope/tip identification, access direction and relevant image settings; identify processed copies and retain originals.Request another view where focus, glare, shadow or obstruction prevents the agreed visual assessment.
Coverage and dispositionRecord whether each required region was viewed, partly viewed or not viewed, alongside its separate observation and disposition status.Keep missing coverage distinct from an adverse observation; obtain the applicable release decision for each.

Place the check in the manufacturing handoff

Before machining-route approval, review access on the controlled model, including any later assembly that would close a passage. Ask the inspector to confirm the proposed tip and approach against the actual geometry. Resolve inaccessible regions while the route and quoted evidence can still be changed.

Agree the inspection stage relative to deburring, finishing, final cleaning and packaging. Have the cleaning owner approve contact and handling restrictions, preparation of the inserted equipment, and whether further cleaning is required afterward. Give inspection and packaging teams the same release sequence.

At inspection, reconcile the actual part, processing stage and passage map before recording. Preserve the original files and connect each observation to its map entry. If an approved subsequent operation changes an observed region, ask which images and other acceptance checks must be repeated before shipment.

When an entrance view leaves the root unresolved

Suppose a hypothetical record shows the entrance of passage P07, but its specified root region remains in shadow. Mark the root coverage incomplete. Ask for another approved approach or view; if access remains unavailable, obtain a documented scope disposition. A clear entrance image should close only the visual area it shows.

If the new view shows a line-like indication, retain both the location view and the closer image. Have the authorized reviewer decide what additional examination or other evidence is needed. Require permission before blending or deburring the area, then record any approved work and subsequent check against the same passage identifier.

Agree separate evidence when size or form matters

Evident explains stereo measurement using paired lenses and parallax. It describes calibrating the stereo tip to its videoscope and discusses object distance and image sharpness when selecting corresponding points. [2]

Bring the record requirements into quotation review

Start with a non-confidential description of the component, passage access and requested visual records. Agree confidentiality and file transfer before sharing controlled drawings. Ask the quotation to identify the proposed inspection provider, included coverage, excluded regions, deliverables and unresolved technical decisions.

Inspection scope and documentation are defined during quotation according to drawing requirements and application needs.

Geetai coordinates drawing-led manufacturing through long-term partners without presenting partner facilities as Geetai-owned.

Frequently asked questions

Does an unmarked video establish complete passage coverage?

Request the passage map and region-to-file links. Reconcile every required region and obtain dispositions for missing views before closing the agreed visual record.

Can a clean-looking passage establish vacuum-service approval?

Use the visual record only for its agreed observations. Have the responsible technical owner define the separate cleanliness and application evidence required for the intended service.

Related review paths

More from Blog

References

  1. The Definitive Guide to Remote Visual Inspection — Waygate Technologies, a Baker Hughes business. Accessed 2026-11-21T02:38:12.125Z.
  2. Advancements in Remote Video Measurement: Get More Precision from Farther Away — Evident. Accessed 2026-11-21T02:38:12.126Z.

Drawing-led review

Move from general guidance to drawing review

Share the controlled drawing, material, quantity and verification requirements for project-specific review.

Discuss Your Drawing